Project Name: Psychology Site Migration
Staff Guidance: Andre
Description: Working on migrating Psychology content to the new Cascade site. Department Area information migrated. Needs some more clean-up. Need to contact Alex for some more content, ask Suloni to design right navigation, and organize Google Doc. Deadline is Mid-August!
Completion Status: In progress
Project Name: Susanna Cascade Training
Staff Guidance: Suloni, Andre
Description: Tutorial on the ins and outs of Cascade.
Completion Status: DONE
Project Name: Canvass Training
Staff Guidance: Emily
Description: Explore Canvass and gain knowledge to assist faculty members in the Canvass pilot in the Fall. Will take existing LAITS site and convert it to Canvass (design and all).
Completion Status: In progress
Project Name: COLA Homepage Weekly Updates
Staff Guidance: Andre
Description: Updating new Video Podcast on theCOLA Homepageeach week.
Completion Status: 7/30/12 update in progress
to be continued…
Date Assigned: July 6th
Project Name: STA Logo Tutorial Feedback
Staff Guidance: Suloni
Description: Feedback on STA Logos!
Completion Status: DONE, everyone did an amazing job 🙂
Date Assigned: July 2nd
Project Name: COLA Homepage Weekly Updates
Staff Guidance: Andre
Description: Updating new Video Podcast on theCOLA Homepageeach week.
Completion Status: DONE
Date Assigned: June 21st
Project Name: Footprint Ticketing System
Staff Guidance: Suloni, Andre
Description: Trying out the Footprint ticketing system!
Completion Status: In progress, collected data and will send out feedback
Date Assigned: June 15th, 19th, 20th, 22nd
Project Name: Cascade Maintenance and permissions
Staff Guidance: Suloni, Andre
Description: Magistra – fix the design. TLC – new permissions. Immigration Studies – graduate student function implementation. E3W – graudate student function implementation.
Completion Status: Reassigned
Date Assigned: June 15th
Project Name: COLA Pages Address Clean-Ups
Staff Guidance: Andre
Description: Clean up the formatting for the COLA pages on the Resource Offices areas.
Completion Status: Reassigned
Date Assigned: June 8
Project Name: Lab Cleanup
Staff Guidance: Suloni
Description: Desktop cleanse, browser set up, and clean in preparation for New STAs/Summer
Completion Status: In progress
Date Assigned: Mar 6, April
Project Name: Korean Homepage
Staff Guidance: Suloni
Description: Design with Katie a homepage for the new Korean Instructional site.
Completion Status: Final Splash image approved and ready for mock-ups
Date Assigned: May 8
Project Name: STA Flyers Update
Staff Guidance: Suloni
Description: Updating the 2012 STA Job posting information.
Completion Status: In progress